Boardwalk Site Cleared and Ready

  • waterfrontbaddeck
  • May 19
  • 1 min read

Demolition of the old boardwalk began on schedule and went smoothly thanks to an efficient crew and beautiful weather. More than 75 tons of debris were removed and transported to the Baddeck Waste Transfer Station, and the boardwalk site has now been fully cleared and prepped for the next phase of work. Much of the wood from the demolition was taken for reuse by community groups and individuals.

Looking ahead, Tuesday of this week will bring the start of the watermain installation, a critical part of this broader infrastructure project. As this phase begins, we will keep everyone updated on traffic control measures and do our best to minimize disruptions in the village. Pile driving equipment should be on-site toward the end of the week. Stay tuned for more updates, and be sure to follow along as the next phase of the projects unfolds.


Drone photos courtesy of Barry Watson and Booke Oland

 
 
 

Recent Posts

See All
Road Closure at Boardwalk Site Only

PUBLIC NOTICE: ROAD CLOSURE – WATER STREET Please be advised that Water Street will be closed at the boardwalk site only, starting...

 
 
 
Project Update – June 11th

We are making steady progress on the boardwalk project. The first phase of the waterline installation is now nearly complete. We have...

 
 
 