top of page

Boardwalk Site Cleared and Ready

  • waterfrontbaddeck
  • May 19
  • 1 min read

Demolition of the old boardwalk began on schedule and went smoothly thanks to an efficient crew and beautiful weather. More than 75 tons of debris were removed and transported to the Baddeck Waste Transfer Station, and the boardwalk site has now been fully cleared and prepped for the next phase of work. Much of the wood from the demolition was taken for reuse by community groups and individuals.

Looking ahead, Tuesday of this week will bring the start of the watermain installation, a critical part of this broader infrastructure project. As this phase begins, we will keep everyone updated on traffic control measures and do our best to minimize disruptions in the village. Pile driving equipment should be on-site toward the end of the week. Stay tuned for more updates, and be sure to follow along as the next phase of the projects unfolds.


Drone photos courtesy of Barry Watson and Booke Oland

 
 
 

Recent Posts

See All
Volunteer – Boardwalk Demo Day

We had a great day on Saturday as volunteers removed boards from the Baddeck boardwalk in preparation for construction. It was a bit of a...

 
 
 

The Baddeck Community Wharf is owned and managed by the Village of Baddeck. Floating docks are owned by Build Nova Scotia. For inquires other than dock reservations and information, please contact: waterfront@baddeckvillage.ca or call 902-295-3666 © 2025 Village of Baddeck All Rights Reserved

Screen Shot 2021-02-19 at 5.55.42 AM.png
bottom of page